site-map Home > Other Stuff > Free Property And Investing Articles > Sub-division Costs

www.PropertyBooks.com.au


The Centre For All You Need To Know About Property Investing

 

SUBDIVISION COSTS
 Paul Tooze 

One of the most common mistakes made by fledging Developers is underestimating what people refer to as “Subdivision Costs”.

 

What is a “Subdivision Cost?" 

I always think of Subdivision Costs as being the cost for all the work required to get your separate titles issued.  This work will vary from one Subdivision to the next. Some common examples of work required for separate titles are Headworks (Water Corp fees), Surveyors fees, new power dome, new sewer junction and site clearing. 

And how much will the Subdivision Cost? 

This is a commonly asked question and the answers you will get can vary quite dramatically. I quite often hear people mention that they have allowed $20,000 to $30,000 because somebody else has told them to.  Never rely on these estimates in your calculations before choosing a site, I’ll show you why. Below are some costing examples for what most people would consider to be subdivision works.

 

Water Corporation Headworks fee.…………………………………………………………………….$6500

Surveyors Survey Strata Fees………………………………………………………………………….. $5400

Western Powers Power Dome.………………………………………………………………………….. $1500

New Sewer Junction…………………………………………………………………………………………… $3000

Clear Site (Remove rubbish, lawn, trees, sheds etc)….………………………………… $15000

 

Total……………………………………………………………………………………………………………………$31400

 

Now what about all the items that you didn’t think about or weren’t told about?

 

You may need to extend the sewer main………………………………………………………. $13000

What if there was a pool in the backyard…………………………………………………………. $5000

What if your council needed a constructed and drained driveway………………… $4000

What if you need a brick store room…………………………………………………………………..$8000

 

The list goes on and on. Your $31400 could now be $61400 So as you can see there is no specific amount to allow for Subdivision Costs.  You need to analyze what items are required to get your titles through, allow an amount for each item, and then work out your total.
If you want to know more, and there is so much more that you need to know, take a look at the book.
Full recognition is given to Brett Taylor for this article.